Terling, Hatfield Peverel, Essex
The nature of work to be carried out was as follows:
- To Strip the old asbestos sheeting and re-sheet the gable end with single skin slate blue coloured cladding.
- Install USB's and steel angles ready for the installation of a roller shutter door and personnel door.
- Lay block work to either side of the personnel door and roller shutter door.
- Install slate blue coloured flashings and drip flashing.
- Supply and install a steel fire exit door, slate blue in colour.
- Supply and install a 3 phase power operated roller shutter door in galvanised finish.
- Remove all plastic sheeting from the side of the building and replace with single skin, slate blue coloured cladding.
- Remove all existing rain water goods and replace with black PVC storm flow guttering.
Project Completed February 2009