Wimbish Green, Saffron Walden
The nature of work to be carried out was as follows:
- The safe dismantling of all grain handling equipment for the customer to display in his museum.
- The safe dismantling of the sheltered grain pit.
- The safe dismantling of all crittall and concrete bins.
- To strip and re sheet the gable end and one side of the building in single skin olive green coloured sheets.
- Supply and install USB's and steel angles ready for the installation of the personnel door and roller shutter door.
- Supply and install a steel personnel door.
- Supply and install a galvanised roller shutter door.
- Concrete in fill the grain pit and conveyor tunnel.
- Remove all existing rainwater goods and replace with black PVC storm flow guttering.
Project Completed November 2008